Checking bolt connections
Effort 0 – 2 h
1. If not already done for other inspection purposes, shut-down the PCS6000 according to “PCS6000 Lockout/tagout procedure”, 3BHS600000 E22.
2. Check tightness of power conductor bolt connections:
• Make visual checks of the torque markings on the bolts (Fig. 4–1).
• If the torque markings on a screw are out of alignment, check torque of screw connection. The required torque is listed in
Table 10–2 in section 10.4.1, Correct tightening torques of bolted connections, page 135.
• If a connection is loose, tighten the bolt using a torque wrench, then check also the torque of all other connections (the probability is high that if one connection is loose also other connections are loose).
• Torque markings of bolts that have been released and/or re-tightened must be cleaned and newly applied.
NOTICE The capacitors bushing will be damaged when excessive force is applied.
DO NOT exceed the maximum tightening torque when tightening the capacitor terminals. For the appropriate tightening torque of all screws and especially for the screws of the capacitors refer to section 10.4.1, Correct tightening torques of bolted connections, page 135.
After completing all work – if no further inspections have to be performed – restart the PCS6000 according to section 5.4, Start-up after maintenance or troubleshooting, page 70.
Cleaning
The PCS6000 contains components which are sensitive to electrostatic discharge. Electrostatic-sensitive precautions must be applied and suitable tools must be used when cleaning boards and assemblies:
▶ Clean with special care using anti-static brushes and a vacuum cleaner.
▶ Dirt and dust on the electrical components can cause malfunctions and component failures!
▶ DO NOT use compressed air to clean the control system cabinets or converter under any circumstances.
▶ Dirt can be spread uncontrollably this way, which could lead to the corresponding malfunctions.
▶ DO NOT use alcohol or solvents when cleaning inside the cabinets or any electrical components.
Cleaning is necessary if dirt or dust accumulation (also called fouling) occurs within the converter. This could lead to thermally activated accelerated aging, which can be prevented by periodically cleaning.
Procedure:
1. Shut down the PCS6000 according to the “PCS6000 Lockout/tagout procedure”, 3BHS600000 E22.
2. Clean the room carefully with a vacuum cleaner. In the area around the converter, use a soft nozzle tube in order not to damage any components.
3. If necessary, clean the components with a dry cloth.
4. Clean all air inlets and outlets of the cabinets.
5. Clean the air inlets and outlets on all door and roof fans.
6. Restart the PCS6000 according to section 5.4, Start-up after maintenance or troubleshooting, page 70.
Replacing components
Replacement means exchange of components as part of the maintenance schedule or as a consequence of performed visual inspection or performance checks.
The procedures to replace components are described in chapter 7, Checking control components, page 81 or in chapter 10, Replacing power and cooling components, page 133. The corresponding sections are depicted in the following table.
For replacement tasks without a description of the replacement procedure in this service manual, always shut-down the PCS6000 according to “PCS6000 Lockout/tagout procedure”, 3BHS600000 E22 Switch off the corresponding MCB (see electrical diagram) before replacing the component. Restart the PCS6000 according to section 5.4, Start-up after maintenance or troubleshooting, page 70.
DC-link performance check
Effort 0 – 2 h
The DC-link charging for performance check is performed via the test module of the converter HMI.
IMPORTANT! The measurement results are compared to the nominal values in the “PCS6000 Preventive maintenance report”, 3BHS600000 E84.
The deviation of the measured values from the nominal values is grouped in 3 categories:
– OK: The measurement result is in the expected range.
– Monitor: The measurement result is near the limit.
The respective component is still OK, but it makes sense to compare previous and future measurements to monitor a trend, as well as to compare similar measurements taken with the same instrument.
– Action: The respective component might be faulty and should be replaced.
Procedure:
1. Shut down the PCS6000 according to the “PCS6000 Lockout/tagout procedure”, 3BHS600000 E22.
2. Close all doors.
3. Open DC-link grounding switch.
4. Charge the DC link up to +/-500V.
5. Record the discharging time from +/-500 to +/-200V.
6. Record the discharge time in the Preventive Maintenance Report.
7. If the converter is a 2CL system, repeat the test with the second conversation line.
8. After completing all work, restart the PCS6000 according to section 5.4, Start-up after maintenance or troubleshooting, page 70.
DC-link component check
Effort 4 – 8 h
The DC-link component check has to be done as described below, if the procedure in section 4.4.5, DC-link performance check, page 56 shows a deviation from the nominal value more than 10%.
IMPORTANT! A standard multimeter with capacitance measuring function (up to 10 mF) is required to perform these measurements.
The measurement results are compared to the nominal values in the Preventive Maintenance Report. The deviation of the measured values from the nominal values is grouped in 3 categories:
– OK: The measurement result is in the expected range.
– Monitor: The measurement result is near the limit.
The respective component is still OK, but it makes sense to compare previous and future measurements to monitor a trend, as well as to compare similar measurements taken with the same instrument.
– Action: The respective component might be faulty and should be replaced.
Procedure:
1. Shut down the PCS6000 according to the “PCS6000 Lockout/tagout procedure”, 3BHS600000 E22.
2. Double check that the DC-link is grounded (ground switch).
3. Remove reinforcement plates and the ASM10 (Auxiliary Supply Module).
4. Disconnect the three sets of measurement the wires (1, 2 and 3) which connect the DClink capacitors (C701…C703) to the converter.
5. Record the serial number of each capacitor in the Preventive Maintenance Report.
6. Measure the capacitance of Grid side Power Module Capacitors (see electrical circuit diagram POMxx).
7. Measure the capacitance of Generator side Power Module Capacitors (see electrical circuit diagram POMxx).
8. Reconnect the wires/busbars from the converter with the marked tightening torque (see separate sticker on the capacitor) to the capacitors.
NOTE – If the tightening torque is not specified on the capacitor, use tightening torque defined under section 10.4.1, Correct tightening torques of bolted connections, page 135.
9. After completing all work, restart the PCS6000 according to section 5.4, Start-up after maintenance or troubleshooting, page 70.
Filter components performance check
Effort 2 – 4 h
IMPORTANT! A standard multimeter with capacitance measuring function (up to 10 mF) is required to perform these measurements.
The measurement results are compared to the nominal values in the Preventive Maintenance Report. The deviation of the measured values from the nominal values is grouped in 3 categories:
– OK: The measurement result is in the expected range.
– Monitor: The measurement result is near the limit.
The respective component is still OK, but it makes sense to compare previous and future measurements to monitor a trend, as well as to compare similar measurements taken with the same instrument.
– Action: The respective component might be faulty and should be replaced.
The filter components performance check comprises the following 3 parts:
– Grid side filter components performance check (see section 4.4.7.1, Grid side filter components performance check, page 59)
– Neutral point performance check (see section 4.4.7.2, Neutral point performance check, page 61)
– dv/dt filter components performance check (see section 4.4.7.3, dv/dt filter components performance check, page 61)
Grid side filter components performance check
Shut down the PCS6000 according to the “PCS6000 Lockout/tagout procedure”, 3BHS600000 E22.
Double check that the DC-link is grounded (ground switch) and the grid side is grounded (grounding kit).
Disconnect the PE wire to -R544:2 in cabinet +A12. (see electrical circuit diagram HFMxx).
Measure the resistance of -R544 between -R544:2 (the disconnected pin) and -R544:1.
Measure the capacitance between -X541/2:3 and -X541/2:4 (12 capacitors parallel, when grid side grounded).
6. Reconnect the removed connection.
7. After completing all work, restart the PCS6000 according to section 5.4, Start-up after maintenance or troubleshooting, page 70.
Neutral point performance check
1. Shut down the PCS6000 according to the “PCS6000 Lockout/tagout procedure”, 3BHS600000 E22.
2. Double check that the DC-link is grounded (ground switch).
3. Disconnect the wire from:
• +A23-R461 pin2
• +A23-R462_1 pin1
• +A23-R463 pin 1
See electrical circuit diagram NCM10
4. Measure the capacitance of -C461 between -C461:1 and Ground.
5. Measure the resistance of -R461 between -R461:1 and -R461:2.
6. Measure the resistance of -R462 (over both two resistances) between -R462_1:1 and Ground.
7. Measure the resistance of -R463 between -R463:1 and -R463:2.
8. Measure the resistance of -R463 between -R464:1 and -R464:2
9. Reconnect the removed connections.
10. After completing all work, restart the PCS6000 according to section 5.4, Start-up after maintenance or troubleshooting, page 70.
dv/dt filter components performance check
1. Shut down the PCS6000 according to the “PCS6000 Lockout/tagout procedure”, 3BHS600000 E22.
2. Double check that the DC-link is grounded (ground switch) and the generator side is grounded.
3. Measure the resistance of -R581 and -R582 (connected in series) in cabinet +A11 between -R581:2 and -R582:1.
4. Measure the resistance of -R583 and -R584 (connected in series) in cabinet +A11 between -R583:2 and -R584:1.
5. Measure the resistance of -R585 and -R586 (connected in series) in cabinet +A11 between -R585:2 and -R586:1.
6. (see electrical circuit diagram VFMxx)
7. Measure the capacitance between -C581:2 in cabinet +A11 and Ground (7 capacitors parallel when generator side grounded).
8. Measure the resistance between -C581:2 in cabinet +A11 and Ground. The measurement is passed when Rmeasured rises to OL (OverLoad).
9. After completing all work, restart the PCS6000 according to section 5.4, Start-up after maintenance or troubleshooting, page 70.
Functionality and security procedure
1. Shut down the PCS6000 according to the “PCS6000 Lockout/tagout procedure”, 3BHS600000 E22.
2. Visually check the cable connections to the grid breaker (GRB).
3. Check the properly fixation of the contact block of the Local Emergency Button +A40.
4. Check whether the maintenance of the GRB has been done according to the manufacturer’s specifications.
IMPORTANT! All the points of the following tests have to be confirmed by ticking the corresponding check boxes in the Preventive Maintenance Report.
5. Perform the “Local Emergency Button test” according to the procedure given in the
Preventive Maintenance Report.
During this test the different paths of the GRB open command will be checked. Each path (-X910:5, -X910:8, -X910:9, -X910:11) is tested with the other paths disconnected.
For each test case, the GRB must open when the Local Emergency Button +A40 is pressed.
6. Perform the “Door interlocking test” according to the procedure given in the Preventive
Maintenance Report.
During this test the proper function of all door interlocks will be checked.
7. Perform the “Grounding isolator interlocking test” according to the procedure given in the Preventive Maintenance Report.
WARNING! For the grounding isolator interlocking test, the GRB disconnector must be in test position!
• During this test the interlocking function between GRB and DC-link grounding isolator has to be confirmed, ie, the GRB cannot be closed unless the DC-link grounding switch is open and locked; and the DC-link cannot be grounded if the GRB Disconnector is closed or simulated to be “closed” via the HMI button.
• If the locking supervision contact is not used, the interlocking has to be confirmed as follows: The GRB cannot be closed if the DC-link grounding isolator is closed, whereas the DC-link grounding isolator cannot be closed if the GRB is closed.
8. Perform the “Safety interface to upper level control test” according to the procedure given in the Preventive Maintenance Report.
During this test the safety interface communication from the WTC (Wind Turbine Control) to the converter and from the converter to the WTC will be checked.
9. Perform the “UPS Supply Check” according to the procedure given in the Preventive Maintenance Report.
This test procedure is used to verify the proper functionality of the Uninterruptible
Power Supply (UPS).
10. After completing all work, restart the PCS6000 according to section 5.4, Start-up after maintenance or troubleshooting, page 70.
Related product recommendations:
3BHE057276R0001 ABB
3BHE05222R0001 ABB
3BHE052222R0001 ABB
3BHE052226R0001 ABB
3BHS536315 E13 ABB
3BHS868401 E27 ABB
3BHS354969 E01 ABB
3BHS868401 E16 ABB
3BHS868401 E13 ABB
3BHS856856 E29 ABB
3BHE046085E16 DLU75
3BHE046085E16 ABB
3BHE057277E16 CCA2
3BHE057277E16 ABB
3BHE034201E16 WCM10
3BHE034201E16 ABB
3BHE046081E16 DLU74
3BHE057852E16 PCM12
3BHE057852E16 ABB
3BHE046081E16 ABB
3BHE051397E16 POM72
3BHE051397E16 ABB
3BHE051398E16 POU72
3BHE051398E16 ABB
3BHE054801E16 GBM51
3BHE054801E16 ABB
3BHE055094E16 GBU72
3BHE055094E16 ABB
3BHE056532E16 CCU14
3BHE057825E16 PCM12
3BHE057825E16 ABB
3BHS868401E16 ABB
3BHS866401E27 ABB
3BHE055094E47 ABB
3BHE044916E27 ABB
3BHE056532E26 ABB
3BHE05632R0001 ABB
3BHE056532E16 GRB2
3BHE056532E16 ABB
More…


ABB PCS6000
Medium voltage wind turbine converter
Designed for larger turbines, ABB’s medium voltage full power converters are characterized by low parts count, high availability and minimized losses. The higher voltage level of MV converters means lower currents in the electrical drivetrain, along with an easier integration of the converter into the turbine. The converters can be designed for nacelle or tower base installation, and their modularity allows easy customization to meet customer requirements. Fault ride-through and grid code compliance capabilities are also provided.
Key product features
Full power converter, water cooled
4 – 15 MW
3.3 kV, 4-quadrant, 3-level NPC topology
IGCT semiconductor technology
High efficiency (>98%)
Compact and modular design
Suitable for tower base or nacelle installation
IEC & UL certified
Grid compliance
Native cloud access
https://www.weikunfadacai1.com/2025/09/12/pcs6000-preventive-maintenance-for-medium-voltage-wind-turbine-converters-cca2-fr-q-hx-ul-3bhe057277r0001/
ABB PCS6000 Medium voltage wind turbine converter
ABB PCS6000 is a modular, water-cooled multi-level converter for medium-voltage wind turbines. It directly interfaces with higher-voltage generators, eliminating the need for a gearbox and heavy-duty low-voltage cabling. This design significantly boosts efficiency, reduces losses, and enhances overall system reliability. Its compact footprint and full low-voltage ride-through capability make it an ideal, powerful solution for modern multi-megawatt wind energy applications.
ABB ACS 6000 3BHB906001446 System Integration ACS6000 Medium voltage driver
ABB ACS 6000 medium voltage drive provides the optimum solution for applications where high power and maximum reliability is required. Since its introduction, the ACS 6000 has gained an excellent reputation for high quality and reliability. As a result ABB has worldwide one of the largest installed bases of medium voltage multidrives incorporating the latest technology.
ABB ACS 6000 is a modular drive designed for the most demanding single-motor or multi-motor applications. The optimum configuration for each application is reached by combining the standardized modules resulting in lower investment costs and a smaller footprint. The ACS 6000 is available with several different inverter modules in the power range from 3 to 13 MVA.
Several motors can be linked to the ACS 6000 via the common DC bus, enabling multi-motor operation with only one multidrive converter. A multidrive, common DC bus converter principle offers a solution with optimum efficiency.
S-093N 3BHB009885R0001
S-093N 3BHB009885R0021
S-093N 3BHB009885R5311
S-093N 3BHB006457R0001
S-093H 3BHB030478R0309
S-123H 3BHB030479R0512
S-073H 3BHB030477R0207
3BHB009885R0104 S-093H
3BHB009885R0063 S-093M
3BHB009885R0052 S-093H
3BHB009885R0032
3BHB009885R0031 S-093S
3BHB009885R0021 S-093N
3BHB009885R0014 S-093M
3BHB009885R0013 S-093M
3BHB009885R0004 S-093H
3BHB009885R0002 S-093H
3BHB009885R0001
3BHB009884R0204 S-073H
3BHB009884R0052 S-073H
3BHB009884R0022
3BHB009884R0021 S-073N
3BHB009884R0013 S-073M
3BHB009884R0004 S-073H
3BHB009884R0002 S-073H
3BHB009884R0001
ACS6000 Medium Voltage AC Drive System Phase Controller 3BHB906001446 ABB
https://www.weikunfadacai1.com/2025/09/12/pcs6000-preventive-maintenance-for-medium-voltage-wind-turbine-converters-cca2-fr-q-hx-ul-3bhe057277r0001/